Marine Link
Thursday, November 21, 2024

VIDEO: Liebherr Debuts Lift Height Extension of STS in Australia

Maritime Activity Reports, Inc.

January 18, 2023

  • The leg extensions are put into place. Image courtesy Liebherr
  • The STS has been jacked up, waiting for the extensions to be moved into place. Image courtesy Liebherr
  • The leg extensions are put into place. Image courtesy Liebherr The leg extensions are put into place. Image courtesy Liebherr
  • The STS has been jacked up, waiting for the extensions to be moved into place. Image courtesy Liebherr
The STS has been jacked up, waiting for the extensions to be moved into place. Image courtesy Liebherr

Liebherr Container Cranes completed its first ship to shore lift height increase with their new patented jacking system as part of Liebherr Transform. The operation was conducted under the supervision of Liebherr engineers at Patrick Terminals – Brisbane Autostrad.

Patrick Terminals – Brisbane Autostrad located on the eastern coast of Australia is one of the world’s most advanced container terminals. Liebherr have two ship to shore container cranes at the terminal, a new STS currently being commissioned and an STS supplied in 2015. The 2015 crane has a supplied lift height of 37.5 m, but with larger vessels calling at the port, a lift height extension was required.

Liebherr have been carrying out lift height extensions for many years, but in 2022 a new patented jacking system for lift height extensions, was deployed at the Brisbane terminal for its first use. Designed and built in Liebherr Container Cranes in Ireland, one of the key features of the system is that it uses the crane’s end carriage as a solid base for jacking the crane structure, eliminating the requirement for additional equipment. 

Furthermore, since the system uses the crane structure as a basis for jacking, the loadings are low and are carried through the existing crane.

Preparation takes a couple of weeks and the system allows the crane to be jacked in position or moved back from the rails for jacking if required. 

The actual crane raise and the insertion of the extensions can be completed in a number of hours and so is suited to terminals prone to high winds. The operation is exceptionally quick and the whole process can be completed from as little as four weeks per crane. Following completion of the project, the jacks are containerised and shipped onwards for their next deployment.

Major project in Port of NY/NJ

GCT New York LP operates four Liebherr ship to shore container cranes. Supplied in 2004, the cranes have a lift height of 36.57 m and an outreach of 50 m. Working in partnership with Liebherr USA, GCT will undertake a significant Liebherr Transform project to extend the lift height of the cranes by 8.6 m and the outreach of the cranes by 5 m (two bays). When complete, the cranes will have the ability to work the largest vessels currently calling the port of NY/NJ allowing GCT to better service their customers.

Below is Liebherr's video documenting the lift height extension of the STS crane in Patrick Terminal – Brisbane Autostrad.



Subscribe for
Maritime Reporter E-News

Maritime Reporter E-News is the maritime industry's largest circulation and most authoritative ENews Service, delivered to your Email five times per week