Marine Link
Saturday, November 23, 2024

Van Oord Completes Deutsche Bucht Offshore Installation

Maritime Activity Reports, Inc.

April 5, 2019

Dutch maritime contracting company Van Oord has completed the installation of the offshore substation at the 269 MW Northland Power’s Deutsche Bucht offshore wind farm in Germany`s Exclusive Economic Zone.

The supersize substation with a 2,700-tonnes topside is the centrepiece of the wind farm. It houses all electrical equipment needed to transform the power from the 33 turbines to a higher voltage for further transmission, said a press release from the company specializes in dredging, land reclamation and constructing man made islands.

The unmanned offshore substation consists of an upper part, the topside, and a lower part, the jacket foundation. The two components were assembled in Vlissingen, the Netherlands, and transported to the project site on floating barges.

After the 61- metre -high jacket was installed on the seabed, the 19 -metre -high topside was lifted and mounted on top of it. The top deck of the offshore substation reaches to approximately 40 metres above the sea level. A helicopter landing platform allows access to the platform for operation and maintenance work.

Construction of the Deutsche Bucht offshore wind farm, owned by Canadian-based global power producer Northland Power, is in full swing.

The wind farm will supply enough renewable energy to meet the needs of approximately 328,000 households per year. As the balance of plant contractor for the project, Van Oord is responsible for the design, engineering, procurement, construction and installation of the foundations, inter array cables and offshore substation, and the transport of the wind turbines.

Commissioning of the wind farm is expected to take place in the second half of 2019.

Subscribe for
Maritime Reporter E-News

Maritime Reporter E-News is the maritime industry's largest circulation and most authoritative ENews Service, delivered to your Email five times per week