Marine Link
Friday, November 8, 2024

Offshore Charging Station Tested on Hybrid Construction Vessel

Maritime Activity Reports, Inc.

September 10, 2024

Source: Seaonics

Source: Seaonics

Norwegian lifting and handling specialist Seaonics has tested its Ocean Charger solution on an electric service operation vessel (SOV).

High-voltage charging tests were conducted to charge the batteries on Rem Offshore’s diesel-electric hybrid construction SOV, REM Power, in port as well offshore from a charging point (cable reel, winch and control system) mounted on a wind turbine.

"At 10 years old, the turbine is one of the smallest offshore but the prototype proved it is possible to install the Ocean Charger on an existing turbine and charge an SOV from day one, using 11 kilovolt (KV) current delivering 6MW of charge. Apart from a handful of improvement points to fix, the concept and control system are complete and the product is available for sale as is. We're first in the market and already in talks with wind farm owners," said Bjørnar Huse, Sales Manager, Offshore Energy at Seaonics.

He adds that because power current varies between wind parks and wind turbines, the commercial version will have to be customized for each project.

"Connecting vessels to the power grid in the wind farm and charging batteries regularly is a big step towards increasing sustainable operations without using any additional energy sources. It saves the time and energy needed to return to port to charge, while the operating cost of electric SOVs versus diesel and alternative fuels is much lower, because both the energy is cheaper and you reduce engine maintenance demands. You still need diesels for back-up power but quite a lot smaller than for a full diesel operation, with lower Capex," said Huse.

A large, 60-person SOV consumes 20 to 25MW hours per day, so at 6MW you can potentially charge for a full day's operation in three to four hours. "But it's better for the lifetime of the battery pack to never be completely depleted nor fully charged – between 50 and 80% is best. You could charge for six hours at night, say, then do ad-hoc charging during the day," Huse said.

Meanwhile, wind farm owners are moving away from the idea of locating charging points on a substation or expensive floating buoys, he says. "The standard will most likely be to locate the charging point on a turbine. Downscaling the weight and cost also means you can have many charging points reducing the need to cruise long distances to charge. The turbines are usually owned by the developer, so they can fit as many as required. It is easier mechanically to have charging points on a substation but as these are usually owned by the grid owner, there is some doubt as to who would be responsible for their maintenance and insurance etc. This will have to be sorted out project by project.”

The Ocean Charger's solution uses an industry-standard connector plug and power levels both for offshore charging and in port. "The prototype worked using a standard vessel and crane. The plug is an industry standard used for shore charging cruise ships as well as Hoegh Autoliners' Aurora-class hybrid-electric newbuild car carriers. Tying known technology together made it easier to get to a prototype in a relatively short time. We didn't have to invent a lot of new components unlike some competitors using a bespoke plug," Huse said.

The product can be fitted to any structure and vessel and the power integrated with the vessel switchboard and the chosen charging voltage. "The main development challenges were handling the medium/high current coming on board the vessel and navigating the relevant standards (IEC, ISO etc) for marine technical equipment. For example, there are a lot of class requirements on safety distance around the plug. Existing standards also mostly still cover shore-based equipment so we had to make an offshore version of the different components," Huse added.

Discussions are currently underway with wind park owners regarding charging current. Wind parks usually have 66 or 132KV requiring one or two transformers – one on the charging point and another on the vessel – to get the high voltage down to medium or low voltage. "Some have asked us to explore bringing 132KV, which is the standard current in big power lines on land, directly onto the vessel and do all the transformation onboard. However, managing such high current would require a very bespoke handling and safety system. Feasibility depends on the cost of power integration and transformers," said Huse.

"The cost-effective compromise is to stick with 11KV, which is what the Aurora-class vessels use but is still high considering the standard shore connection for fishing vessels and small SOVs today is typically 690 or 1,000 volts, using the same equipment for both offshore and shore charging."

The SOV approaches the charging point and uses a crane equipped with a gripper that 'grabs' the end of the cable and pulls it onto the connection area integrated on the vessel deck. The REM Power has a fully 3D compensated crane and can connect even in rough weather, but smaller SOVs and maintenance craft that don't have a crane can use the motion-compensated gangway instead. "High accuracy isn't necessary, as the automated handling system guides the plug to the right place, eliminating any need for manual operation," said Huse.

The vessel has to be on DP during charging but with a larger footprint to reduce power consumption. The cable is slack so the vessel can move 20 metres or so back and forth without damaging anything. The system has been designed with two levels of redundancy for emergency release.

"It is of course possible the plug may occasionally be released in a non-orderly manner and be submerged, leading to water intrusion both in the plug and cable. That may require the whole cable to be replaced involving time and cost. No industry standard plugs have been approved or are capable of being submerged, so we had to design a watertight cover. The handling system opens the cover when the plug is on board and guides it into the charging notch, and in reverse when charging is complete."

Huse says it would take a few months to customise the configuration and get approvals for a specific wind park and vessel.

The Ocean Charger was developed by a consortium led by Ålesund-based Vard Design and sister companies Seaonics and Vard Electro, alongside partners Rem Offshore, Solstad Offshore, SINTEF Energi, SINTEF Ocean, DigiCat, Sustainable Energy, Equinor, Source Galileo Norge, Corvus Energy, Plug, Shoreline, Sustainable Energy, University of Bergen, Norce and Maritime CleanTech.

Subscribe for
Maritime Reporter E-News

Maritime Reporter E-News is the maritime industry's largest circulation and most authoritative ENews Service, delivered to your Email five times per week