Panama Canal Issues RFP for Excavation Projects
http://www.pancanal.com/eng/procsales/buy.html
The excavation involves the removal of 7.5 million cubic meters in a stretch of approximately 2.4 kilometers, which will serve as the entrance of the new Pacific access channel.
"Three weeks ago, the world watched as we broke ground on expansion with the beginning of the first dry excavation. Now we have initiated phase two of this crucial project," said Executive Vice President of Engineering and Program Administration Jorge L.
Quijano. "Expansion is on track and we look forward to selecting the best firm for the job, as we work to complete all five dry excavation projects and create the new Pacific access channel."
The scope of work for the second dry excavation project includes the construction of a new section of road and a new crossing over the Cocoli River, in addition to the removal and/or relocation of electrical utilities, telecommunication lines, water lines, sanitation lines, ducts and sewers.
Important dates in the process include an October 2 site visit. This will be followed by an inspection of the geological core, where interested parties will learn about the type of material in the area. The ACP will also host an informational meeting on October 4.