Marine Link
Tuesday, November 26, 2024

Metal Shark Puts First Two Citywide Ferries on the Water

Maritime Activity Reports, Inc.

March 2, 2017

  • (Photo: Tony Broussard – Berard Transportation)
  • (Photo: Tony Broussard – Berard Transportation)
  • (Photo: Tony Broussard – Berard Transportation)
  • (Photo: Tony Broussard – Berard Transportation)
  • (Photo: Tony Broussard – Berard Transportation) (Photo: Tony Broussard – Berard Transportation)
  • (Photo: Tony Broussard – Berard Transportation) (Photo: Tony Broussard – Berard Transportation)
  • (Photo: Tony Broussard – Berard Transportation) (Photo: Tony Broussard – Berard Transportation)
  • (Photo: Tony Broussard – Berard Transportation) (Photo: Tony Broussard – Berard Transportation)
Louisiana-based shipbuilder Metal Shark said it has put the first two passenger vessels for New York's new Citywide Ferry Service on the water, having splashed the new builds at its Franklin, La. shipyard late last week.
 
At 7:30 a.m. on February 24, operators from Berard Transportation began the process of moving the first of two 86' x 26' catamaran-hulled aluminum passenger vessels from Metal Shark's final assembly building to the waiting cranes from H. Brown Crane Service, which hoisted the vessel and placed it into the adjacent Charenton Canal. By 3:30 p.m., both vessels were in-water with Metal Shark crews resuming work on vessel fitout.
 
Meanwhile, two more Citywide Ferries were being prepared for paint, and two others were taking shape in the welding shop, as Metal Shark is currently building six of the Incat Crowther-designed, 149-passenger, USCG Subchapter T passenger ferries for HNY Ferry Fleet LLC (a Hornblower company), operator of New York's Citywide Ferry Service. 
 
"Today with the launch of these first two vessels we reached an important milestone on the Citywide Ferry project, which we commenced in July," said Metal Shark CEO, Chris Allard. "We're on a rigorous schedule to get these boats completed and delivered on time. Fortunately we had planned the bulk of the logistics prior to the award of the contract, and we're happy to say we're right on schedule."
 
Metal Shark plans to deliver two of the New York ferries per month from March through May.
 
“It is a massive undertaking and Metal Shark has and continues to showcase their experience and expertise in the craft of vessel construction,” noted Junior Volpe, Director of Special Projects for Hornblower. “The vessels constructed will become part of an impressive fleet operating on the East River in New York this coming summer.”
 
In addition to Metal Shark’s six ferries, Horizon Shipbuilding is also building 13 Citywide ferries at its shipyard in Bayou La Batre, Ala., with the first deliveries planned for spring 2017.
 
Meanwhile, site preparation is taking place at the Metal Shark yard as the builder expands its operations to accommodate increased activity. The foundation for a new 200' x 80' fully enclosed large vessel assembly building will be poured within the next few weeks, along with a stand-alone, two-story office building with over 8,000 square feet of space for Franklin's engineering, program management, and administrative staff.
 
With Citywide Ferry construction now well underway and portion of an 18-boat foreign military patrol boat order recently completed, Metal Shark is preparing to commence work on a four-boat order of 88' passenger vessels for the Potomac Riverboat Company division of Entertainment Cruises, and a two-boat order of 105' passenger vessels for the New Orleans Regional Transit Authority. Beyond the passenger vessel market, the Franklin yard will be producing a range of orders including additional 45' patrol boats, a 45' pilot boat, a multi-boat US Navy contract for 50' high-speed vessels, a 70' supply boat, and a 158' catamaran.

Subscribe for
Maritime Reporter E-News

Maritime Reporter E-News is the maritime industry's largest circulation and most authoritative ENews Service, delivered to your Email five times per week