MV Chenega to be Delayed
“The latest word we have from Derecktor Shipyards in Bridgeport, Conn., is that, due to problems with the shipyard’s electrical subcontractor, delays have been incurred with the equipment testing, dockside and sea trials. The Chenega will not be delivered until late April or as late as May 1,” said AMHS General Manager John Falvey. “In light of that extended delivery date, we will deploy the Aurora to Prince William Sound in late spring to provide the service the residents of that area expect.”