DNV GL Issues Guidance on Inspection Planning

November 19, 2015

The low oil price and a reduction in newbuilds have driven the integrity of existing assets up the agenda for the oil & gas industry. However, the cost of inspection programs can be significant, adding to the operational costs.

DNV GL has now launched a recommended practice (DNVGL-RP-C210) providing the first international guidance on how to establish a sound basis for in-service inspection planning for fatigue cracks in marine structures. The guidance will save operational costs by using a risk-based approach to identify the ‘hot spots’ requiring inspection.
 
The cost of inspections of marine structures such as jackets, semi-submersibles and floating production vessels can put a strain on already challenged operational budgets, driving the need to develop inspection programs only addressing critical areas.

Photo: DNV GL
Photo: DNV GL


“What we are commonly experiencing, is the use of inconsistent inspection planning methodologies, which can result in costly inspections at non-critial areas, or worse, no inspection at critical areas," says Kjell Eriksson, Regional Manager for Norway in DNV GL - Oil & Gas.
The cost reduction is obtained by reducing the overall inspection and maintenance scope, still ensuring continued cost-efficient safe operation of the asset. This is done by using risk based methods in identifying the critical areas, so-called ‘hot spots’, that needs to be inspected and non-critical areas that do not need further assessment.


“Fatigue crack can cause significant damage to offshore structures. The critiallity of fatigue cracks can vary, which combined with costly inspections programs drives the importance of developing accurate methods for identification of fatigue critical areas,” says Gudfinnur Sigurdsson, Technology Leader, Marine Structures, DNV GL - Oil & Gas. “The use of risk based inspection planning for identification of critical aras for inspections will result in reduced inspection program and thereby a corresponding significant reduction in the inspection and operational costs."


In-service inspection for fatigue is carried out to assure that possible cracks in the structure do not exceed a critical level. The outcome of in-service inspections can then be used to update the estimated fatigue reliability of the structure.


The RP includes guidance on:

DNVGL-RP-C210 is based on the findings of a DNV GL led joint industry project (JIP) completed in 2013.