Indonesian Navy Frigate Completes Sea Trials
The first of two SIGMA 10514 PKR naval frigates for the Indonesian Navy has successfully completed its sea trials as of September 7, marking a milestone on a project for which the first steel was cut in January 2014.
The assessment phase began with seven days of basin trials to ensure that the propulsion and safety systems were fully operational before the vessel made the challenging passage from the PT PAL shipyard in Surabaya to the open waters of the Java Sea. There then followed two weeks of sea trials that included tests of a weapons system and the combat radar and commissioning of the sonar. Noise measurements and cavitation observations were also carried out.
The trials were successful, with almost all the systems passing their assessments first time around, according to shipbuilder Damen. Some elements, such as the accommodation, require minor modifications and these will be undertaken prior to three days of final tests at the end of September.
The 105-meter, 2,365-metric-ton PKR frigates are designed to undertake a wide range of missions in and around the waters of Indonesia. Their primary mission is anti-air, anti-surface and anti-submarine warfare. However, they are also equipped for maritime security, search and rescue, and humanitarian support tasks.
The two vessels have been/are being been built using a collaborative modular process operating simultaneously at Damen Schelde Naval Shipbuilding (DSNS) in the Netherlands and PT PAL shipyard in Indonesia. Each is made up of six modules, and for the first vessel four of these were built at PT PAL. The other two were built and fully tested at DSNS in the Netherlands before being shipped for final assembly at PT PAL.
The shipbuilder said the success of the program rested on the two yards working together with the end client operating almost as a single unit. The strong relationship also allowed the massive technology-transfer program to proceed smoothly, both in Indonesia and in the Netherlands.
The first Sigma 10514 is on schedule for delivery at the end of January 2017 following the completion of three months of crew training. Meanwhile, work is currently proceeding in both the Netherlands and Indonesia on the second vessel in the contract.