Hapag-Lloyd AG v Skyros Maritime Corp: Late Redelivery and Lost Opportunities

April 14, 2025

The English Commercial Court (the “Court”) has provided helpful clarity on the extent of damages available to a claimant shipowner for the late redelivery of a vessel under a time charter where there is evidence that the owner of the vessel would have been unable to enter into a subsequent charter for the vessel. In such circumstances, only nominal damages will be recoverable, as no actual loss has been suffered.

Background

Key Issues

The English Commercial Court (the
The English Commercial Court (the “Court”) has provided helpful clarity on the extent of damages available to a claimant shipowner for the late redelivery of a vessel under a time charter where there is evidence that the owner of the vessel would have been unable to enter into a subsequent charter for the vessel. Credit: Adobe Stock/nmann77

The key issue to be considered by the Court was whether, as a matter of legal principle, the Owners were entitled to claim the difference between the charter rate and the market rate, notwithstanding the fact that they would not have been better off, in monetary terms, if there had been no breach (due to their inability to enter into subsequent charters under the MOAs).

The Owners presented three key arguments, based on the principles of quantum meruit, user damages and negotiated damages, all of which were accepted by the arbitrators in their decision.

A further set of arguments were also put forth in favour of the doctrine of res inter alios acta, as canvassed in Transfield Shipping Inc v Mercator Shipping Inc [2008] UKHL 48 (“The Achilleas”), which the Owners used to suggest that the MOAs, and consequently the restriction preventing the entry into further fixtures, should be disregarded as irrelevant in the assessment of damages.

Decision

The Court allowed the Charterers’ appeal, and in doing so, found as follows:

Quantum Meruit:

The quantum meruit argument was swiftly rejected on the basis that this principle is one of restitution/unjust enrichment which can only apply where services are rendered without any agreement as to their renumeration. In this case, the claim was for breach of the redelivery obligations; the hire was earned and paid at the charter rate. Therefore, the agreement for all the services rendered was properly abided by and the Charterers did not receive a service that was outside of the contemplation of the Charters, hence making quantum meruit inapplicable.

User Damages:

The Court displayed similar dissatisfaction for the user damages argument. This principle allows for parties to claim more than nominal damages where their property has been wrongfully used. It was held that whilst the failure to deliver the Vessels on time was wrongful, this did not constitute improper use of property.

Further, the Owners had not been deprived of possession of the Vessels, even if the Charterers also had simultaneous use of the Vessels in the sense of being able to issue voyage instructions. It was stated that the applicability of user damages to contract is highly limited.

Negotiating Damages:

The third line of arguments from the Owners, i.e. negotiating damages, was also deemed inappropriate. Negotiating damages are generally only available where a claimant has been deprived of the economic value of a right which has been breached (for example, the breach of an intellectual property agreement would deprive the claimant of the economic value of a right). The economic value of the right is treated as a valuable asset. The Court agreed with the proposition put forth by leading commentaries that the obligation to make timely redelivery cannot be said to create or protect a valuable asset. In other words, timely redelivery did not provide the Owners with a right of any economic value.

Remoteness and the principle of res inter alios acta:

The Owners had made a further and separate argument during the arbitration process that the MOAs with the buyers were res inter alios acta, i.e., the MOAs were too remote to be taken into account in determining the claim for damages. The core disagreement between the parties turned on the issue of whether the doctrine of remoteness can operate to increase, rather than reduce, damages, with the Charterers arguing that remoteness cannot expand recovery to allow an innocent party to recover damages for losses it has not suffered.

The Owners had first relied on the judgment in The Achilleas, a case in which an owner was held not to be entitled to claim an increase in damages by relying on a subsequent fixture. The Court disagreed with the Owners’ interpretation of the judgment and deemed it to be “wholly unrealistic”. Further, the Court held that The Achilleas had been decided on an orthodox application of the principles of remoteness to prevent an award of damages for loss that was not foreseeable. In doing so, the court in The Achilleas had abided by the usual rules of the compensatory principle, through which subsequent contracts not contemplated by the parties cannot be considered in the calculation of damages. It was deemed inappropriate to suggest that the effects of this analysis would be to allow for recovery of damages by a claimant who has suffered no loss at all.

It was ultimately held that the principle of res inter alios acta had little to do with the present case. The MOAs could not be ignored for being too remote or unrelated to the case at hand, as their provisions directly resulted in there being no actual loss suffered. The Court concluded by providing support for the views expressed in various textbooks; where owners have not lost the opportunity to take advantage of the market rate during the period of overrun, there is no scope for substantial compensation of this kind to arise.

Importantly, the Court found that because it was the MOAs that prevented the Owners from entering the market, they had suffered no recoverable loss from missed market opportunities. Owners were therefore not entitled to recover substantial damages because of the late redelivery and were only entitled to nominal damages.

Key Takeaways

Related News

INTERCARGO Welcomes ILO Recognition of Seafarers as Key Workers ABS' Wiernicki to Retire at the End of 2025 UK Court: Shipbuilder Privinvest Can Appeal Over "Tuna Bond" Case Huisman to Equip Capital Offshore’s PSVs with Four Cranes Shell to Complete Marine Survey at Venezuela Gas Field Ahead of License Cancellation