Durban’s 90-year-old Dry Dock Set for Repair

July 22, 2015

The 90-yer-old Prince Edward Graving Dry Dock in Durban, which is owned and operated by Transnet National Ports Authority (TNPA), will be undergoing a R30 million ($2.4 million USD) repair project on its outer caisson over the next four months. This is the third and final phase of a repair program on the structure, which was deemed unsafe and in need of repair due to the dry dock’s age and general need for maintenance.
Earlier this month, TNPA appointed Durban-based engineering firm Channel Construction as the successful bidder after a competitive tender process in which the company satisfied all technical, BBBEE and price evaluation criteria. Channel Construction will work closely with managing contractor, Sebata Group, which is overseeing the project, with technical expertise and quality assurance provided by a team including KwaZulu-Natal’s only naval architecture firm, Naval Africa. 
The 35-meter-long, 900 ton outer caisson at the Prince Edward Graving dock in Durban will be undergo a $2.4 million refurbishment project over the next four months. (Photo: Transnet National Ports Authority)
Left to right: Sibusiso Nhlabathi, TNPA Durban Port Engineer; Rishaan Chabilal, Sebata Group Mechanical Engineer; Martin Cloete Channel Construction Project Manager and Moshe Motlohi TNPA, Durban Port Manager, in front of the decommissioned caisson at the Prince Edward Graving Dock in the Port of Durban(Photo: Transnet National Ports Authority)
The 35-meter-long, 900 ton outer caisson at the Prince Edward Graving dock in Durban will be undergo a $2.4 million refurbishment project over the next four months. (Photo: Transnet National Ports Authority)
Left to right: Sibusiso Nhlabathi, TNPA Durban Port Engineer; Rishaan Chabilal, Sebata Group Mechanical Engineer; Martin Cloete Channel Construction Project Manager and Moshe Motlohi TNPA, Durban Port Manager, in front of the decommissioned caisson at the Prince Edward Graving Dock in the Port of Durban(Photo: Transnet National Ports Authority)
Durban Port Manager, Moshe Motlohi said, “The contractor’s preferred method required a four month nonoperational period of the dry dock. However TNPA has implemented a contingency plan in consultation with the project management team to reduce this period to two months in order to minimize the impact on industry.”
“We have thoroughly investigated various methods, including an option of keeping the dry dock operational during the entire project implementation phase of four months and the associated risks,” Motlohi continued. “We are however confident that the method we have adopted will afford protection against risks such as endangering the structural integrity of the caisson and dock, escalating costs and prolonged duration of the project.”
The repair project is expected to run from July to November 2015, with the nonoperational period occurring over August and September. TNPA confirmed that no repair bookings had been received from industry for the nonoperational period of two months and there would be a vessel in the dock for service during July for a 20-day period and another in October. The dock’s current market includes cargo vessels and TNPA’s own fleet of marine vessels.
Channel Construction would work 24-hour shifts with the majority of the work to be carried out offsite at the contractor’s Bayhead workshop. Work will include demolition and waste disposal, structural repair, welding, modification and replacement of structural members and plates, design and fabrication certification, commissioning and final handover. 
TNPA expects the Durban dry dock outer caisson repair to be completed in November and it would be commissioned when there is a vessel scheduled to depart from the dry dock during this month.
Motlohi said the outer caisson repair project forms part of TNPA’s structured program for the dry dock, which would include a concrete refurbishment program, replacement of crane rails, replacement of two aged electrical overheard cranes and refurbishment of the inner caisson. Also included in this program is the procurement of new Jib cranes, mechanical pump house upgrade, replacement of Workshop 24 equipment, installation of a new firefighting system, installation of new Capstans, replacement of the floating dock and procurement of six compressors. 
TNPA is meanwhile fast-tracking investments into ship repair facilities nationwide. The authority has identified projects to the value of R16.8 billion ($1.4 billion) aimed at facilitating the growth of the local ship repair, ship building and oil and gas sectors. All of the projects are set to be operational by 2019.
These plans dovetail with the South African government’s Operation Phakisa initiative which aims to unlock the economic potential of South Africa’s oceans, estimated to have the potential to create just over one million jobs and contribute up to R189 billion ($15.3 billion) to South Africa’s gross domestic product (GDP) by 2033.
Refurbishment of existing ship repair facilities will see an estimated R2.2 billion ($177.8 million) invested into mechanical, electrical and civil infrastructure upgrades at the Ports of Durban, East London, Port Elizabeth, Cape Town and Mossel Bay. Greenfield projects to the total tune of R14.6 billion ($1.2 billion) will include new capacity creation at the Ports of Saldanha, Richards Bay and East London. These will be co-funded through public-private partnerships (PPPs) guided by transaction advisors.

Related News

Maersk says Global Trade could rise 7% in 2025 Weaving the Basket of Solutions BIMCO's Shipping Number of the Week Panama Canal Battles Ongoing Drought Lock Accident Closes Germany's Mosel River