Dredging: Managing the Impact of Channel Deepening and Widening on Surrounding Structures

April 3, 2020

U.S. ports have worked toward increasing the depth and width of their channels to allow for larger ships with greater capacities. The equation is generally: bigger ships = more throughput = increased profitability. But what are the impacts around a channel after it’s widened? The ripple effects may go further than you think.

Managing the Impact of Channel Improvement Projects on Structures and Pipelines
With more water to impact them, structures around an expanded channel may need improvements, and pipelines under the channel may need relocation to make way for dredging. Streamlining the process to account for these changes takes a considerable amount of early coordination and collaboration amongst stakeholders.

Photo: Scott Dobry Pictures
Photo: Scott Dobry Pictures
About the Authors: Brent Moore manages HDR’s ports and maritime practice on the Gulf Coast and is experienced in all aspects of marine projects from planning to design to construction administration.
About the Authors: Neil McLellan is a senior project manager at HDR who leads multi-disciplined maritime teams along the Texas and Louisiana Gulf Coast. He has nearly 40 years of coastal engineering experience, including work on the multi-year Port of Houston Channel Development Project and a federal feasibility study to deepen the Brownsville Ship Channel for the Brownsville Navigation District Channel Improvement Project. Thanks to our contributing authors: Paul Bearden, Christine Magers and S
Photo: Scott Dobry Pictures
Photo: Scott Dobry Pictures
About the Authors: Brent Moore manages HDR’s ports and maritime practice on the Gulf Coast and is experienced in all aspects of marine projects from planning to design to construction administration.
About the Authors: Neil McLellan is a senior project manager at HDR who leads multi-disciplined maritime teams along the Texas and Louisiana Gulf Coast. He has nearly 40 years of coastal engineering experience, including work on the multi-year Port of Houston Channel Development Project and a federal feasibility study to deepen the Brownsville Ship Channel for the Brownsville Navigation District Channel Improvement Project. Thanks to our contributing authors: Paul Bearden, Christine Magers and S

Many disciplines of expertise are required to make these channel deepening projects happen — from engineers (coastal, geotechnical, structural, electrical, civil and more) to environmental scientists and permitting specialists who help comply with the federal, state and local regulatory laws to protect the environment.

Ripples Affecting Docks, Bridges and Bulkhead Structures

Many structures are situated on or around shipping channels such as dock facilities (including wharf and jetty platforms, mooring and breasting structures, approachways and catwalks) bridges, navigation towers, coastal floodwalls, piers and bulkheads. When channels are expanded, each of these structures is influenced by the ripple of more water in a deeper and wider channel. As the original built environment changes, owners of these structures must reassess their structural and geotechnical integrity.

Facility Capacity

If dock owners want to take advantage of the expanded channel and service larger, more efficient ships, they need to determine the serviceability of their facilities. These larger ships typically require additional mooring and berthing capacities, berthing depth and overall size (length and width) adjustments, and at times, modifications and/or upgrading of the existing mechanical equipment like loading arms, hoses, piping and gangways. For the facility to handle increased structural and throughput loads, owners must undertake studies like passing vessel analyses, maneuverability assessments, integrity analyses of existing structures, equipment operational envelope studies, mass balance studies and existing component condition assessments. These studies can be involved and require a methodical process. They often take considerable time to complete. Facility owners can save time and money when accounting for these studies early in the planning and execution stages of channel deepening and widening projects.

Photo: Scott Dobry Pictures

Pipeline Relocation Ripple
Countless pipelines and tunnels run underground in and around shipping channels. Pipelines that may be uncovered or disturbed during dredging must be moved, requiring pipeline operators to plan for impacts on their businesses. As with impacted terminal facilities and docks, engineering analysis of soils, environmental mitigation and new permits are required for each pipeline relocation. From an overall cost and project schedule perspective, there are significant benefits in pipeline operators and port authorities working together during data acquisition, and particularly in geotechnical and regulatory phases. Early engagement of channel improvement project stakeholders and consultants is helpful as pipeline operators anticipate forecasted pipeline outage times during relocation.

How Is All of This Funded?

A variety of sources — public, private and public-private partnerships — fund channel improvement projects.

Government Versus Private Funding

When more private funding is involved in an improvement project, it typically decreases the time needed to get the project designed and constructed because there are less procedures and requirements. If the federal government is involved, the minimum standard for deep draft navigation projects is divided into 75% federal and 25% non-federal funding. For most cases when federal funds are involved, the federal government pays for the ongoing maintenance of the ship channel after the deepening and widening improvements are completed. Channel maintenance — continued dredging to keep the channel in the desired location — over the years can far exceed the initial capital improvement costs, so partnership with the federal government can save considerable expense over the project’s life. Project stakeholders need to weigh the options carefully to find the best funding balance.

Who Pays for the Ripples?
Dock and structure improvements are typically the owner’s responsibility to maintain and upgrade as needed whether the owner is benefitting from the channel deepening and widening project or not. All navigation projects operate under their own guidelines and regulations. Therefore, there is no standard for funding pipeline relocations. Cost apportionment for publicly funded channels will be different from private channels. Cost sharing for channels developed by the federal government and supported by a local sponsor (likely the port) will change based on when the channel project was “authorized” by Congress. The current guidance indicates the local sponsor is responsible for half the pipeline relocation cost, and the pipeline owner is responsible for the remainder. Upgrades to pipelines are the pipeline owner’s responsibility. In rare cases, the local sponsor or the federal government will remove abandoned pipelines.

Economic Impact to Pipeline Operators
While substantial work and investment is required to relocate pipelines, many pipeline operators see an economic benefit when the effort leads to greater quantities of their product shipping to new markets. But what about the pipeline owners who may not benefit from the channel deepening and widening projects? Those pipeline operators incur unintended costs for little to no return on investment. Collaboration between all channel deepening and widening project stakeholders can minimize costs for pipeline owners and others. For example, all stakeholders need to understand what’s happening in the subsurface through geotechnical engineering investigations — though pipeline owners may need deeper geotechnical information for pipeline relocation designs than ports. To reduce expenses, those impacted could share the mobilization, demobilization and equipment costs for completing the geotechnical borings once. Not all stakeholders will require exactly the same data, but with careful communication and planning, resources can be combined and costs shared.

How Do We Best Prepare for the Ripples of Channel Deepening and Widening Projects?
Channel improvement projects ripple into many different areas and require much attention and coordination among port owners and the owners of structures, facilities and pipelines which are affected. Coordination, communication and cooperation between the various stakeholders along a channel often lead to a more efficient port. This can also result in a more profitable business environment for the beneficiaries of the channel improvement project, and result in more efficient handling of goods and services for the end user and/or market being served.